Phase 2

Phase 2 Construction Progress

99 %

Work completed Week of 5/30/16

  • Located sanitary sewer services for directional drilling of water main on Kimball Avenue
  • Installed 12-inch water main via open cut from Route 176 to 228 Kimball Avenue

 

Work Scheduled for Week of 6/6/16

  • Installation of 12-inch water main along Kimball Ave. from 228 Kimball to Hammond Ave. via a combination of open cut construction and directional drilling.

 

Work Completed Week of 12/5/16

  • Finished installation of water service connections on Lakeshore Blvd.
  • Roadway patching on Lakeshore Blvd., Sheridan Drive and Grand Blvd.
  • Water main connections at Lakeshore Blvd. and Hill St.
  • Startup of Bonner Road PRV Station
  • Repair water man leak on old main on Route 176 at Lakeshore Blvd.

 

Work Scheduled Week of 12/16/16

  • Possibly no activity due to weather
  • If weather permits, may work on piping modifications at Well No. 4 for new PRV

 

Work Completed Week of 11/28/16

  • Installation of additional water service connections on Lakeshore Blvd.
  • Branch water main connections at Lakeshore Blvd. and Highland Ave and at Well House No. 4
  • Roadway patching on Lakeshore Blvd. and Sheridan Drive

 

Work Scheduled Week of 12/5/16

  • Continue to install water services on Lakeshore Blvd.
  • Finish roadway patching on Grand Blvd. and Sheridan Drive

 

Work Completed Week of 11/21/16

  • Installation of water services on Lakeshore Blvd.
  • Abandoning old water main along Route 176
  • Curb and gutter, sidewalk and driveways restoration is segment 7

 

Work Scheduled for Week of 11/28/16

  • Continue to install water services on Lakeshore Blvd.
  • Make branch water main connections on Lakeshore Blvd.

 

Work Completed Week of 11/14/16

  • Made water main connections at the following locations:
    • Grand Blvd and Grant Place
    • Grand Blvd and Pershing Drive
    • Sheridan and Madison
    • Sheridan and Monroe
  • Installed service connections on Route 176 between Hill St. and Lakeshore Blvd.
  • Installed topsoil, seed and blanket at various locations within segment 7

 

Work Scheduled Week of 11/21/16

  • Installation of water services on Lakeshore Blvd.
  • Sidewalk, curb and gutter, and driveway restoration in segment 7 and Segment C

 

Work Completed Week of 11/7/16

  • Made water main connection at Grand Blvd. and Wauconda Road
  • Waiting for chlorination tests to pass for Lakeshore Blvd. watermain

 

Work Scheduled for Week of 11/14/16

  • Make water main connections at Grand Blvd and Grant Place, Grand Blvd and Pershing, Sheridan and Madison and Sheridan and Monroe
  • Cut in valve and hydrant on Bonner and Monroe

 

Work Completed Week of 10/31/16

  • Made water main connections at Grand Blvd and Edwards
  • Pressure tested water main and Lakeshore Blvd between Route 176 and Grand Blvd

 

Work Scheduled Week of 11/7/16

  • Complete chlorination of water main on Lakeshore Blvd
  • Make connection to existing 12-inch water main at Lakeshore Blvd and Grand Blvd

 

Work Completed Week of 10/24/16

  • Installation of 12-inch water main on Lakeshore Blvd from Lakeshore Drive to Grand Blvd
  • Installation of fire hydrants on Lakeshore Blvd

 

Work Scheduled Week of 10/31/16

  • Wake water main connections at Grand Blvd and Grant Place, Grand Blvd and Pershing, and Grand Blvd and Edwards
  • Upon successful chlorination, start installation of water services on Lakeshore Blvd
  • Restoration repairs in segment 6

 

Work Completed Week of 10/17/16

  • Installation of 12-inch water main on Lakeshore Blvd from 609 Lakeshore to Lakeshore Drive
  • Installation of 12-inch water main on Lakeshore Blvd and Grand Blvd
  • Installation of water main on Sheridan Road from Madison Street to Monroe Street
  • Pressure tested and chlorinated water mains at Grand Blvd and Grant Place, Grand Blvd and Pershing, and Grand Blvd and Edwards

 

Work Scheduled Week of 10/24/16

  • Installation of 12-inch water main via open cut on Lakeshore Blvd from Lakeshore Drive to Grand Blvd
  • Upon successful chlorination, start installation of water services on Lakeshore Blvd

 

Work Completed Week of 10/10/16

  • Installation of 12-inch water main on Lakeshore Blvd. from Sunnyside Ave North approx. 825 ft.
  • Installation of water main at Grand Blvd and Pershing, Grand Blvd. and Grant Place, and Grand Blvd. and Edwards
  • Completed driveway and pavement restoration in segment 6
  • Completed landscape restoration on Ridge Street and Route 176
  • Continued chlorination of water main along Route 176

 

Work Scheduled Week of 10/17/2016

  • Continue installation of 12-inch water main on Lakeshore Drive via open cut and directional drilling
  • Installation of water main on Sheridan Drive from Madison to Monroe

 

Work Completed Week of 10/3/16

  • Installation of 12-inch water main on Lakeshore Blvd. through Hill Street intersection and across Sunnyside Ave.
  • Installation of pressure connection at Grand Ave and Grant Place
  • Driveway, pavement, and sidewalk restoration in Segment 6

 

Work Scheduled for Week of 10/10/16

  • Continue installation of 12-inch water main on Lakeshore Blvd via open cut from Sunnyside Ave north
  • Installation of water main at Grand Blvd and Grant Place and at Grand Blvd and Edwards Place
  • Continue chlorination of water main along Route 176 near Lakepoint Condos
  • Complete driveway and pavement restoration in Segment 6

 

Work Completed Week of 9/19/16

  • Water main connection at Lakepoint Condos
  • Complete water main installation via horizontal directional drilling along Route 176 from Hill Street to Lake Shore Blvd
  • Continued water main installation proceeding north on Lake Shore Blvd

 

Work Scheduled Week of 9/26/16

  • Continue installation of 12-inch water main via open cut on Lake Shore Blvd from Highland Ave to Hill Street
  • Install 12-inch water main via horizontal directional drilling on Lake Shore Blvd from Hill Street to Sunnyside
  • Pressure test and chlorinate water main on Route 176 and at Bonner Road PRV Station
  • Disconnect old water main at Route 176 and Ridge
  • New water valves at intersection of Sheridan Drive/ Ridge Ave / Northshore Dr.

 

Work Completed Week of 9/12/16

  • Valve box removed and water main connection and disconnection at Route 176 and Ridge Ave
  • Water main connection at Kimball and Hammond
  • Started water main installation via horizontal directional drilling along route 176 from Hill street to lake Shore Blvd
  • Started water main installation via open cut on Lake Shore Blvd from Route 176 north approx. 86 feet
  • Electrical wiring for Bonner Road PRV station

 

Work Scheduled for Week of 9/19/16

  • Complete water main installation via horizontal drilling along route 176 from Hill street to Lake Shore Blvd
  • Continue water main installation proceeding north on Lake Shore Blvd
  • Connection of new water main to Lakepoint Condominiums

 

Work Completed Week of 9/5/16

  • Installed Bonner Road PRV station
  • Repaired leak on Hammond
  • Installed water services on Hammond
  • Made Water main connections at route 176 and Sundown Ct and at Ridge and Kimball

 

Work Scheduled Week of 9/12/16

  • Start water main installation via horizontal directional drilling along Route 176 from Hill Street to Lake Shore Blvd
  • Valve box removal and water main connection at Route 176 and Ridge

 

Work Completed Week of 8/29/16

  • Installed piping for Bonner Road PRV station and future Bonner Road elevated tank
  • Installed water services on Route 176
  • Formed and poured concrete driveways, curb and gutter, and sidewalks on Kimball and at Main Street and Route 176

 

Work Scheduled Week of 9/5/16

  • Install Bonner Road PRV station
  • Install water services on Hammond
  • Disconnect old water main at Kimball and Ridge
  • Make water main connections at Ridge and Ridge Ct and at Kimball and Ridge
  • Possibly start installation of water main at Hill and Route 176 to Lakeshore Drive

 

Work Completed Week of 8/22/16

  • Disconnection of old water main and removal of old hydrants on Kimball
  • Installation of valve vault at Route 176 and Kimball
  • Begin installation of piping for Bonner Road PRV station

 

Work Scheduled Week of 8/29/16

  • Continue installation of piping for Bonner Road PRV station
  • Installation of water services on Route 176
  • Pending satisfactory chlorination tests, installation of water services on Hammond and disconnects Ridge and Kimball
  • Possibly start pavement restoration on Kimball

 

Work Completed Week of 8/18/16

  • Installation of water services on Kimball from Rout 176 to Lotus, on Ridge from Kimball to Ridge Court, and Lotus from Kimball to Route 176
  • Chlorination, flushing and sampling of water main on Route 176 from Ridge to Sundown Court

 

Work Scheduled Week of 8/22/16

  • Disconnection of old water main and removal of old hydrant on Kimball
  • Installation of valve vault of Route 176 and Kimball
  • Begin installation of piping for Bonner Road PRV station

 

Work Completed Week of 8/8/16

  • Installation of water services on Kimball from Route 176 to Lotus
  • Chlorination and flushing of water main on Route 176 from Ridge to Sundown Court

 

Work Schedule Week of 8/15/16

  • Installation of water services on Kimball from Lotus to Ridge

 

Work Completed Week of 8/1/16

  • No construction activity
  • Pressure tested segment 6 water mains

 

Work Scheduled for Week of 8/8/16

  • Begin installing new water services on Kimball Avenue on Wednesday

 

Work Completed Week of 7/25/16

  • Finish segment 6 water main including valve vaults and hydrants
  • Successfully completed chlorination testing of water mains on Kimball, Lotus and Ridge

 

Work Scheduled for week of 8/1/16

  • Begin installing new water services on Kimball on Tuesday or Wednesday

 

Work Completed Week of 7/18/16

  • Finish directional drilling of water main on Route 176 between Ridge and Sundown Court
  • Installed bored and jacked water main on route 176 and Sundown Court
  • Flushed and re-chlorinated water main on Kimball, Lotus and Ridge

 

Work Scheduled for Week of 7/25/16

  • Finish installed water main, hydrant and valve vault of Sundown Court
  • Install whips in valve vaults for pressure testing and chlorination
  • If disinfection test passes, begin installing new water services on Kimball

 

Work Completed Week of 7/11/16

  • Installation of water main via directional drilling on Route 176 from Ridge east towards Sundown Court
  • Flushed and re-chlorinated water main of Route 176 (Main to Kimball) Kimball, Lotus and Ridge

 

Work Scheduled for Week of 7/18/16

  • Continue installation of water main via directional drilling on Route 176 from Ridge east towards Sundown Court
  • Excavate auger pit at Sundown Court and bore and jack caring pipe under Route 176 Sundown Court
  • If chlorination samples pass, start connection of water services to new water main on Kimball by end of week

 

Work Completed Week of 7/5/16

  • Made open cut connections to directionally drilled water main on Hammond and Kimball
  • Pressure tested and chlorinated water main installed to date on Route 176, Kimball, Lotus, and Ridge
  • Started water main installation via directional drilling on Route 176 from Ridge east towards Sundown Court

 

Work Scheduled for Week of 7/11/16

  • Continue water main installation via directional drilling on Route 176 from Ridge east towards Sundown Court
  • If chlorination samples pass, start connection of water services to new main on Kimball by middle of week

 

Work Completed Week of 6/22/16

  • Water main installation via open cut on Lotus Street from Kimball to Route 176
  • Water main installation via open cut and direction drilling on Route 176 from main Street to Kimball Avenue
  • Preparation for pressure testing of water main installed to date on Route 176, Kimball, Lotus, Hammond, and Ridge

 

Work Scheduled Week of 7/5/16

  • Water main installation via directional drilling on Route 176 from Ridge east towards Sundown Court
  • Make open cut connections to directionally drilled water main on Hammond between Kimball and Route176
  • Pressure testing of water main installed to date on Route 176, Kimball, Lotus, Hammond, and Ridge

 

Work Completed Week of 6/20/16

  • Water main installation via open cut on Ridge Street from 100 feet north of Kimball to Route 176
  • Water main installation via directional drilling on Hammond Street from mid-block to Route 176

 

Work Scheduled Week of 6/27/16

  • Water main installation via open cut on Lotus Street from Kimball to Route 176
  • Water main installation via open cut and directional drilling on Route 176 from Main Street to Kimball Avenue
  • Prepare and test water main installed to date on Route 176, Kimball, Lotus, Hammond and Ridge

 

Work Completed Week of 6/13/16

  • Water main installation via open cut on Kimball Avenue from just west of Hammond to 410 Kimball
  • Water main installation via directional drilling on Kimball from 410 Kimball to 420 Kimball
  • Water main installation via open cut on Kimball from 420 Kimball to Ridge Street and approx. 100 feet north of Ridge

 

Work Scheduled Week of 6/20/16

  • Water main installation via open cut on Ridge Street from 100 North of Kimball to Route 176
  • Water main installation via directional drilling on Hammond Street between Kimball and Route 176
  • Water main installation via directional drilling on Route 176 from Main Street to Kimball Avenue